HOTEL & CONVENTION CENTER BIDS VARIANCE ANALYSIS
May 19, 2006
HARD COSTS
Estimated Cost    Low Bid    Firm   Variance
Abatement   $613,610   $884,000   First Capital Insulation $270,390
Demolition   $1,719,758   $1,360,000   Empire Wrecking -$359,758
Fencing Barricades   $73,758       C  -   -$73,758
Façade Stabilization   $2,888,000   $2,940,000   Caldwell, Heckles & Egan $52,000  Bid Withdrawn
General Conditions   $464,662   $0     -$464,662  In General Trades Bid
Caissons   $1,400,000   $1,085,000   Shelly Drilling -$315,000
General Trades   $10,490,767   $22,292,000   Wohlsen Construction $11,801,233
Site & Utilities   $1,795,464   $2,909,000   Horst Excavating $1,113,536
Concrete   $13,973,585   $16,200,000   Miller , Long & Arnold $2,226,415
Precast Concrete   $2,759,382   $2,554,500   High Construction -$204,882
Masonry   $1,371,330   $1,469,924   Johnson Masonry $98,594
Steel   $4,200,396   $7,886,000   Steel Fab Enterprises $3,685,604
Roofing   $1,297,044   $2,144,000   United States Roofing Corp. $846,956
Glass & Glazing   $2,165,926   $5,089,600   Hershocks, Inc. $2,923,674
Drywall   $6,145,678   $9,133,000   Novinger's, Inc. $2,987,322
Painting   $1,223,804   $1,724,500   M. Gordon & Son   $500,696
Food Service Hood   $50,000         -$50,000
Conveying System   $2,351,980   $2,427,142   Schindler Elevator $75,162
Plumbing   $4,621,621   $4,444,444   W.G. Tomko, Inc. -$177,177
Fire Protection   $1,192,460   $1,197,800   King's Fire Protection $5,340
HVAC   $10,757,779   $10,969,000   Rado Enterprises $211,221
Electrical   $9,016,010   $8,757,000   Farfield Company -$259,010
Telecom/AV   $1,003,463   $664,856   Vistacom Audiovisual -$338,607
Construction Management   $2,790,000   $2,410,000   High Construction/Reynolds Construction -$380,000
TOTAL BID ITEMS   $84,366,477   $108,541,766     $24,175,289
Over Budget 28.66%
Other Hard Costs
Site Acquisition   $2,690,000   $2,690,000
Sunk Operating Costs $2,835,735   $2,835,735
TOTAL HARD COSTS $89,892,212   $114,067,501
         
TOTAL SOFT COSTS  $36,588,073   $36,588,073
         
FINANCING COSTS $13,507,439   $13,507,438 Will need to re-estimated
         
TOTAL PROJECT   $139,987,724   $164,163,012