| HOTEL & CONVENTION CENTER BIDS VARIANCE ANALYSIS | ||||||||
| May 19, 2006 | ||||||||
| HARD COSTS | ||||||||
| Estimated Cost | Low Bid | Firm | Variance | |||||
| Abatement | $613,610 | $884,000 | First Capital Insulation | $270,390 | ||||
| Demolition | $1,719,758 | $1,360,000 | Empire Wrecking | -$359,758 | ||||
| Fencing Barricades | $73,758 | C - | -$73,758 | |||||
| Façade Stabilization | $2,888,000 | $2,940,000 | Caldwell, Heckles & Egan | $52,000 | Bid Withdrawn | |||
| General Conditions | $464,662 | $0 | -$464,662 | In General Trades Bid | ||||
| Caissons | $1,400,000 | $1,085,000 | Shelly Drilling | -$315,000 | ||||
| General Trades | $10,490,767 | $22,292,000 | Wohlsen Construction | $11,801,233 | ||||
| Site & Utilities | $1,795,464 | $2,909,000 | Horst Excavating | $1,113,536 | ||||
| Concrete | $13,973,585 | $16,200,000 | Miller , Long & Arnold | $2,226,415 | ||||
| Precast Concrete | $2,759,382 | $2,554,500 | High Construction | -$204,882 | ||||
| Masonry | $1,371,330 | $1,469,924 | Johnson Masonry | $98,594 | ||||
| Steel | $4,200,396 | $7,886,000 | Steel Fab Enterprises | $3,685,604 | ||||
| Roofing | $1,297,044 | $2,144,000 | United States Roofing Corp. | $846,956 | ||||
| Glass & Glazing | $2,165,926 | $5,089,600 | Hershocks, Inc. | $2,923,674 | ||||
| Drywall | $6,145,678 | $9,133,000 | Novinger's, Inc. | $2,987,322 | ||||
| Painting | $1,223,804 | $1,724,500 | M. Gordon & Son | $500,696 | ||||
| Food Service Hood | $50,000 | -$50,000 | ||||||
| Conveying System | $2,351,980 | $2,427,142 | Schindler Elevator | $75,162 | ||||
| Plumbing | $4,621,621 | $4,444,444 | W.G. Tomko, Inc. | -$177,177 | ||||
| Fire Protection | $1,192,460 | $1,197,800 | King's Fire Protection | $5,340 | ||||
| HVAC | $10,757,779 | $10,969,000 | Rado Enterprises | $211,221 | ||||
| Electrical | $9,016,010 | $8,757,000 | Farfield Company | -$259,010 | ||||
| Telecom/AV | $1,003,463 | $664,856 | Vistacom Audiovisual | -$338,607 | ||||
| Construction Management | $2,790,000 | $2,410,000 | High Construction/Reynolds Construction | -$380,000 | ||||
| TOTAL BID ITEMS | $84,366,477 | $108,541,766 | $24,175,289 | |||||
| Over Budget | 28.66% | |||||||
| Other Hard Costs | ||||||||
| Site Acquisition | $2,690,000 | $2,690,000 | ||||||
| Sunk Operating Costs | $2,835,735 | $2,835,735 | ||||||
| TOTAL HARD COSTS | $89,892,212 | $114,067,501 | ||||||
| TOTAL SOFT COSTS | $36,588,073 | $36,588,073 | ||||||
| FINANCING COSTS | $13,507,439 | $13,507,438 | Will need to re-estimated | |||||
| TOTAL PROJECT | $139,987,724 | $164,163,012 | ||||||